For future reference on outsourced transfers, here are the needs as we are given them by our suppliers:
+
Remember to '''outsource''' 4 CP artwork as '''four color process.'''
-
Jersey...4-5 days from outsourcing to them. 6 days from approval.
 
-
China...7-8 days from outsourcing to them. 9 days from approval.
+
For future reference on outsourced transfers, here are the needs as we are given them by our suppliers:
 +
 
 +
*Jersey...4-5 days from outsourcing to them. 6 days from approval.
 +
*China...7-8 days from outsourcing to them. 9 days from approval.
This is as long as there are no issues with the artwork or colors.
This is as long as there are no issues with the artwork or colors.
Line 10: Line 12:
Additional Information:
Additional Information:
 +
Reminder, if vector files cannot be supplied and redrawing is required on any or all of the components, in most cases, another day needs to be added to the production time.
Reminder, if vector files cannot be supplied and redrawing is required on any or all of the components, in most cases, another day needs to be added to the production time.
-
Spot Color & 4 Color (CMYK) Process orders:
+
 
-
· Pre-flighting is necessary to make sure the artwork meets production
+
Spot Color & 4 Color (CMYK) Process orders:
 +
*Pre-flighting is necessary to make sure the artwork meets production
specifications. This is so that we can supply you with a high quality product.
specifications. This is so that we can supply you with a high quality product.
-
· When artwork is approved, please allow time for production set up.
+
*When artwork is approved, please allow time for production set up.
-
Artwork approval deadline:
+
 
-
· Artwork must be approved by 12 pm in order to take advantage of same
+
Artwork approval deadline:
 +
*Artwork must be approved by 12 pm in order to take advantage of same
day set-up for next day production.
day set-up for next day production.
-
· If approval is received after 12 pm, then setup will begin the next day.
+
*If approval is received after 12 pm, then setup will begin the next day.
Hence, we lose a half day of production time.
Hence, we lose a half day of production time.
-
Receiving:
+
 
-
·Always check with Jake for an accurate “days of production” estimate after
+
Receiving:
 +
*Always check with Jake for an accurate “days of production” estimate after
receiving outsourced transfers.
receiving outsourced transfers.

Current revision

Remember to outsource 4 CP artwork as four color process.


For future reference on outsourced transfers, here are the needs as we are given them by our suppliers:

  • Jersey...4-5 days from outsourcing to them. 6 days from approval.
  • China...7-8 days from outsourcing to them. 9 days from approval.

This is as long as there are no issues with the artwork or colors.


Additional Information:

Reminder, if vector files cannot be supplied and redrawing is required on any or all of the components, in most cases, another day needs to be added to the production time.

Spot Color & 4 Color (CMYK) Process orders:

  • Pre-flighting is necessary to make sure the artwork meets production

specifications. This is so that we can supply you with a high quality product.

  • When artwork is approved, please allow time for production set up.

Artwork approval deadline:

  • Artwork must be approved by 12 pm in order to take advantage of same

day set-up for next day production.

  • If approval is received after 12 pm, then setup will begin the next day.

Hence, we lose a half day of production time.

Receiving:

  • Always check with Jake for an accurate “days of production” estimate after

receiving outsourced transfers.